Summary of workpackages

Work-package no. Workpackage title Lead
contractor
Person-
months
Start
month
End
month
Deliverable
No.
WP-A Substrate Material Selection, Circuit Design and Test Specification TWI 24 1 3 D1, D2, D3 and D4
WP-B Substrate Evaluation using Thermal Processes Epigem 40 3 8 D5 and D6
WP-C Optimisation of Substrate Materials for Thermal Processes BUTE 31.6 8 10 D7
WP-D Evaluation of Optimised Substrate Materials Flex Tech 33.1 10 13 D8 and D9
WP-E Assembly Evaluation using Thermal Processes TWI 19.5 10 15 D10 and D11
WP-F Assembly Evaluation using Alternative Processes Komed 22.9 10 15 D12, D13 and D14
WP-G Investigation of Life Performance Reliability BUTE 19.4 15 19 D15 and D16
WP-H Development of Life Prediction Tools UOG 11.8 19 22 D17, D18 and D19
WP-I Capture and Embedding of Acquired Knowledge TWI 10.8 22 24 D20 and D21
WP-J Project Co-ordination TWI 9.9 1 24 D22, D23, D24, D25 and D26
  Total 223      